A tie-point is a defined physical location where two separate piping systems, scopes of work, or contract packages connect. It establishes the boundary of responsibility between parties; typically between an existing plant and a new facility, between two engineering contractors, or between different construction phases of the same project. Tie-points are documented on P&IDs, piping plans, and a dedicated tie-point register to ensure that both sides of the interface match in terms of size, rating, material, orientation, and location.
Types of Tie-Points
Type
Description
Example
Brownfield tie-point
Connection to an existing, operational piping system
New process unit connected to an existing plant header
Greenfield tie-point
Connection between two new systems designed by different parties or built in different phases
Two EPC packages meeting at a battery limit
Utility tie-point
Connection to plant utility systems (steam, cooling water, air, nitrogen)
New unit receiving steam from an existing boiler
Inter-area tie-point
Connection between different plant areas or units within the same project
Pipe rack transition between Unit 100 and Unit 200
Instrument/electrical tie-point
Signal or power interface between systems
Not piping-specific, but coordinated alongside piping tie-points
Tie-Point Documentation
Document
Content
Tie-point register (list)
Master list of all tie-points: ID number, line number, size, rating, material, flange type and facing, elevation, coordinates, responsible party on each side
Tie-point drawing
Detailed sketch or isometric showing the exact connection arrangement, dimensions, and orientation
P&ID
Tie-points are shown with a flag or symbol indicating the interface boundary and reference to the connecting system
Material grade and corrosion allowance must be compatible
Gasket and bolting
Both parties must agree on gasket type and bolt specification for the connecting flange
Orientation
Flange bolt-hole orientation (straddling the centerline or on the centerline) must be specified
Insulation and tracing
Insulation thickness and tracing continuity across the tie-point must be coordinated
Test boundary
Define which party is responsible for hydrostatic testing the tie-point joint
Tie-points are verified during pre-construction surveys and piping inspections to confirm that the physical arrangement on both sides of the interface matches the approved tie-point register before any connection work begins.
Leave a Comment
Have a question or feedback? Send us a message.