What Is SAT? Site Acceptance Test
FAT vs SAT
| Aspect | FAT (Factory) | SAT (Site) |
|---|---|---|
| Location | Vendor’s facility | Project site |
| Timing | Before shipment | After installation |
| Connections | Simulated I/O, temporary hookups | Actual field wiring, piping, process connections |
| Integration | Standalone or partial integration | Full system integration (DCS, ESD, F&G) |
| Environment | Controlled factory conditions | Actual site conditions (temperature, humidity, dust) |
| Purpose | Verify manufacturing quality and basic function | Verify installed performance and system integration |
Equipment That Requires SAT
| System | SAT Scope |
|---|---|
| Distributed Control System (DCS) | All I/O points verified, control loops tuned, HMI screens confirmed, alarm management tested |
| Emergency Shutdown System (ESD) | Cause-and-effect matrix validated, shutdown sequences tested, voting logic confirmed |
| Fire and Gas Detection | Detector coverage confirmed, alarm/trip logic tested, notification systems verified |
| Motor Control Centers | Motor rotation checks, protection relay settings verified, interlocks tested |
| Actuated valves | Stroke time, fail-safe position, signal response from DCS/ESD |
| Metering systems | Calibration verified against site conditions, communication to DCS confirmed |
| Compressor/pump packages | Performance at site conditions, vibration readings, control system integration |
SAT Procedure
| Step | Activity | Responsible |
|---|---|---|
| 1 | Confirm equipment installation is complete (mechanical completion prerequisites) | Construction |
| 2 | Verify all field wiring, piping connections, and utility hookups | Construction / E&I |
| 3 | Perform loop checks (signal from field device to DCS and back) | Commissioning team |
| 4 | Execute SAT procedure per approved test protocol | Commissioning engineer |
| 5 | Record test results and compare against acceptance criteria | Commissioning team |
| 6 | Generate punch list for any deficiencies | Commissioning lead |
| 7 | Close punch items | Construction / vendor |
| 8 | Sign SAT completion certificate | Project / commissioning manager |
Common SAT Deficiencies
| Issue | Cause | Resolution |
|---|---|---|
| Signal mismatch | Field wiring swapped between terminals | Re-terminate wiring per loop diagram |
| Control loop instability | PID tuning parameters from FAT unsuitable for site conditions | Retune using actual process dynamics |
| Valve stroke time out of spec | Air supply pressure different from factory conditions | Adjust actuator air supply or regulator setting |
| Communication failure | Protocol mismatch between field device and DCS (HART, Modbus, Profibus) | Reconfigure communication parameters |
| Alarm flood | Alarm setpoints not rationalized for site conditions | Review and update alarm management database |
| Grounding issues | Instrument grounding not per specification | Install proper grounding per project electrical spec |
SAT Documentation
| Document | Content |
|---|---|
| SAT procedure | Step-by-step test protocol with acceptance criteria |
| Loop check sheets | Each instrument loop verified from field to DCS |
| Test results | Measured values against specified values |
| Punch list | Deficiencies with priority classification (A, B, C) |
| SAT certificate | Signed confirmation that the system passed SAT |
SAT completion is a prerequisite for pre-commissioning and commissioning. Systems that fail SAT cannot proceed to process fluid introduction. For inspection requirements during construction and hydrostatic testing that precedes SAT, see the detailed guides.