What Is SAT? Site Acceptance Test

FAT vs SAT

AspectFAT (Factory)SAT (Site)
LocationVendor’s facilityProject site
TimingBefore shipmentAfter installation
ConnectionsSimulated I/O, temporary hookupsActual field wiring, piping, process connections
IntegrationStandalone or partial integrationFull system integration (DCS, ESD, F&G)
EnvironmentControlled factory conditionsActual site conditions (temperature, humidity, dust)
PurposeVerify manufacturing quality and basic functionVerify installed performance and system integration

Equipment That Requires SAT

SystemSAT Scope
Distributed Control System (DCS)All I/O points verified, control loops tuned, HMI screens confirmed, alarm management tested
Emergency Shutdown System (ESD)Cause-and-effect matrix validated, shutdown sequences tested, voting logic confirmed
Fire and Gas DetectionDetector coverage confirmed, alarm/trip logic tested, notification systems verified
Motor Control CentersMotor rotation checks, protection relay settings verified, interlocks tested
Actuated valvesStroke time, fail-safe position, signal response from DCS/ESD
Metering systemsCalibration verified against site conditions, communication to DCS confirmed
Compressor/pump packagesPerformance at site conditions, vibration readings, control system integration

SAT Procedure

StepActivityResponsible
1Confirm equipment installation is complete (mechanical completion prerequisites)Construction
2Verify all field wiring, piping connections, and utility hookupsConstruction / E&I
3Perform loop checks (signal from field device to DCS and back)Commissioning team
4Execute SAT procedure per approved test protocolCommissioning engineer
5Record test results and compare against acceptance criteriaCommissioning team
6Generate punch list for any deficienciesCommissioning lead
7Close punch itemsConstruction / vendor
8Sign SAT completion certificateProject / commissioning manager

Common SAT Deficiencies

IssueCauseResolution
Signal mismatchField wiring swapped between terminalsRe-terminate wiring per loop diagram
Control loop instabilityPID tuning parameters from FAT unsuitable for site conditionsRetune using actual process dynamics
Valve stroke time out of specAir supply pressure different from factory conditionsAdjust actuator air supply or regulator setting
Communication failureProtocol mismatch between field device and DCS (HART, Modbus, Profibus)Reconfigure communication parameters
Alarm floodAlarm setpoints not rationalized for site conditionsReview and update alarm management database
Grounding issuesInstrument grounding not per specificationInstall proper grounding per project electrical spec

SAT Documentation

DocumentContent
SAT procedureStep-by-step test protocol with acceptance criteria
Loop check sheetsEach instrument loop verified from field to DCS
Test resultsMeasured values against specified values
Punch listDeficiencies with priority classification (A, B, C)
SAT certificateSigned confirmation that the system passed SAT

SAT completion is a prerequisite for pre-commissioning and commissioning. Systems that fail SAT cannot proceed to process fluid introduction. For inspection requirements during construction and hydrostatic testing that precedes SAT, see the detailed guides.