Skip to content

What Is PWHT? Post-Weld Heat Treatment

Post-weld heat treatment (PWHT) is a controlled heating process applied to welded piping, pressure vessels, and equipment after welding is complete. The primary purpose is stress relief—reducing residual stresses locked into the weld zone by the welding thermal cycle. PWHT also tempers hard microstructures in the heat-affected zone (HAZ), reducing hardness to acceptable levels for sour service and improving ductility.

ASME B31.3, ASME Section VIII, and ASME Section I define mandatory PWHT requirements based on material group, thickness, and service conditions.

When PWHT Is Required

ConditionCode ReferenceRequirement
Wall thickness exceeds code thresholdASME B31.3 Table 331.1.1Mandatory above specified thickness per P-number
Sour service (NACE MR0175)NACE MR0175/ISO 15156Mandatory for carbon steel and low-alloy steel welds to meet max hardness (22 HRC)
Low-temperature serviceASME B31.3May be required to restore toughness after welding
Owner specificationProject-specificOften mandatory for all welds regardless of thickness
Dissimilar metal weldsASME B31.3Based on the material requiring the higher PWHT temperature

PWHT Parameters by Material (ASME B31.3)

P-NumberMaterialMin PWHT Temp (deg C)Hold TimeThickness Threshold
P-1Carbon steel (A106, A234 WPB)593 (1100 deg F)1 hr/25 mm, 15 min minimum>19 mm (3/4 in.)
P-3Low-alloy (A335 P1)5931 hr/25 mm>19 mm
P-4Cr-Mo (A335 P11, P12)704 (1300 deg F)1 hr/25 mm>13 mm (1/2 in.)
P-5ACr-Mo (A335 P22)7041 hr/25 mm>13 mm
P-5BCr-Mo (A335 P91)732 (1350 deg F)2 hr/25 mm minimumAll thicknesses
P-8Austenitic SS (304, 316)Not requiredN/AExempt (PWHT may sensitize)
P-10HDuplex SS (2205)Not requiredN/AExempt (PWHT degrades properties)

PWHT Process Control

ParameterRequirement
Heating rateMax 220 deg C/hr divided by thickness in inches (200 deg C/hr typical for >25 mm)
Soak temperatureWithin specified range (+/- 14 deg C of target)
Soak timePer code table, based on nominal thickness
Cooling rateMax 280 deg C/hr divided by thickness in inches; furnace cool to 400 deg C, then air cool
ThermocouplesAttached directly to the weld/HAZ; minimum number per code/spec (typically 1 per 3 m of weld)
RecordingContinuous time-temperature chart (digital or paper) for QC records
Temperature uniformityMax 83 deg C (150 deg F) variation within the soak band

PWHT Methods

MethodApplicationHeating Source
Furnace PWHTShop fabrication; entire spool piece heated uniformlyGas or electric furnace
Local PWHTField welds; circumferential band of heating elements around weldElectrical resistance heating pads/ceramic heaters
Induction PWHTField or shop; fast heatingInduction coils wrapped around pipe

Local PWHT requires a heated band width of at least 3 times the wall thickness on each side of the weld. Insulation extends beyond the heated band to control the temperature gradient. ASME B31.3 and WRC Bulletin 452 provide guidance on soak band and gradient control band widths.

PWHT Impact on Properties

PropertyEffect of PWHT
Residual stressReduced by 70-90% (primary benefit)
HAZ hardnessReduced (critical for NACE MR0175 compliance)
DuctilityImproved (tempered martensite/bainite)
ToughnessGenerally improved, but can degrade in some Cr-Mo steels (temper embrittlement)
Creep resistanceMaintained if PWHT temperature is below the lower critical transformation temperature
Corrosion resistance (SS)Degraded—sensitization in austenitic SS at 500-800 deg C; never PWHT 300-series SS

PWHT time-temperature records are filed with hydrostatic test reports and mill test certificates in the weld data package, reviewed during pipe inspections.

Read the full guide to non-destructive testing

Leave a Comment

Have a question or feedback? Send us a message.

Your comment will be reviewed and may be published on this page.