What Is HAZOP?
HAZOP Methodology
The HAZOP technique was developed by ICI in the 1960s and is now the globally accepted standard for process hazard analysis in the oil and gas, chemical, and petrochemical industries. It is typically conducted on P&IDs during the detailed engineering phase, after the process design is substantially complete but before construction begins, allowing design changes to be implemented at reasonable cost.
The HAZOP examines the process node by node. A node is a section of the process with a defined design intent (e.g., “transfer crude oil from separator V-101 to heater E-101 at 15 barg and 80°C”).
| HAZOP Element | Description | Example |
|---|---|---|
| Node | Section of process being studied | V-101 outlet to E-101 inlet |
| Design intent | Normal operating condition | Flow at 150 m3/hr, 15 barg, 80°C |
| Guide word | Deviation keyword | NO, MORE, LESS, REVERSE, OTHER THAN |
| Parameter | Process variable | Flow, pressure, temperature, level, composition |
| Deviation | Guide word + parameter | NO FLOW, MORE PRESSURE, LESS TEMPERATURE |
| Cause | What could cause the deviation | Pump trip, valve closed, exchanger fouling |
| Consequence | What happens if the deviation occurs | Vessel overpressure, dry running pump, off-spec product |
| Safeguard | Existing protection | PSV, high-pressure alarm, shutdown system |
| Recommendation | Additional action needed | Add high-level trip on V-101, add check valve on pump discharge |
| Action party | Responsible discipline | Process, instrumentation, operations |
HAZOP Guide Words
The standard guide words, applied systematically to each process parameter, generate a comprehensive list of deviations:
| Guide Word | Meaning | Applied to Flow | Applied to Pressure |
|---|---|---|---|
| NO / NOT | Complete negation | No flow | No pressure |
| MORE | Quantitative increase | More flow (high flow) | More pressure (overpressure) |
| LESS | Quantitative decrease | Less flow (low flow) | Less pressure (underpressure) |
| REVERSE | Opposite direction | Reverse flow | Vacuum |
| AS WELL AS | Additional element | Contamination in flow | Two-phase flow |
| PART OF | Component missing | Loss of one component | Partial blockage |
| OTHER THAN | Complete substitution | Wrong material routed | Different phase |
| EARLY / LATE | Time deviation | Batch too early | Delayed response |
HAZOP Team
A HAZOP study requires a multidisciplinary team:
- HAZOP chairman/facilitator: Leads the study, ensures systematic coverage (independent, experienced in HAZOP methodology)
- Scribe/recorder: Documents all deviations, causes, consequences, and recommendations
- Process engineer: Explains the design intent and process conditions
- Instrument/control engineer: Identifies existing instrumented safeguards
- Operations representative: Provides practical plant operating experience
- Mechanical/piping engineer: Addresses equipment and piping design issues
- HSE representative: Ensures safety and environmental aspects are covered
HAZOP is required by international safety standards (IEC 61882) and is typically a mandatory deliverable in EPC project execution. HAZOP recommendations often drive the design of Safety Instrumented Systems (SIS) and the determination of Safety Integrity Levels (SIL).
Leave a Comment
Have a question or feedback? Send us a message.