Skip to content

What Is FAT? Factory Acceptance Test

A Factory Acceptance Test (FAT) is a formal verification performed at the manufacturer’s facility to confirm that equipment or systems meet the specified functional and performance requirements before shipment. The FAT is witnessed by the buyer’s representative (or a third-party inspector) and must be passed before the equipment is released for delivery.

FATs are standard practice for control systems, packaged equipment, actuated valves, and instrumentation. For bulk piping materials (standard pipes, fittings, flanges), the equivalent verification is the mill inspection per the Inspection and Test Plan (ITP).

What Gets a FAT

Equipment TypeFAT ScopeTypical Duration
Control panels / DCSSoftware logic, I/O checks, alarm testing, HMI verification3-10 days
Motor control centers (MCC)Wiring checks, functional tests, protection relay settings2-5 days
Actuated valve assembliesStroke test, torque verification, fail-safe position, signal response0.5-1 day per valve
Metering skidsFlow accuracy, calibration, communication protocols2-3 days
Compressor/pump packagesPerformance test, vibration, noise, control system integration3-7 days
Fire and gas detection panelsDetector response, alarm logic, cause-and-effect matrix2-5 days

FAT Procedure

StepActivityResponsible
1Vendor prepares FAT procedure based on PO and data sheetsVendor engineering
2Buyer reviews and approves FAT procedureBuyer engineering
3Vendor schedules FAT and notifies buyer (minimum 2-4 weeks advance notice)Vendor
4Buyer or third-party inspector attends FAT at vendor facilityBuyer / TPI
5Tests performed per approved procedure; results recordedVendor with buyer witness
6Punch list issued for any deficiencies or non-conformancesBuyer
7Vendor closes punch itemsVendor
8FAT certificate signed by both partiesBoth
9Equipment released for shipmentBuyer

FAT vs Inspection

AspectFATMill Inspection (ITP-based)
PurposeVerify functional performanceVerify material and dimensional compliance
Applies toPackaged equipment, control systems, assembliesBulk materials—pipes, fittings, flanges, valves
TestsFunctional, performance, software logicChemical, mechanical, NDE, hydrostatic
LocationVendor’s assembly/test facilityMill or forge shop
WitnessBuyer engineer or TPITPI per ITP hold/witness points
OutputFAT certificate and punch listInspection release note (IRN)

Common FAT Deficiencies

DeficiencyExampleImpact
Software logic errorEmergency shutdown sequence executes in wrong orderSafety-critical—must fix before shipment
Wiring errorI/O terminal miswired; signal reads incorrect channelRe-termination required at factory
Calibration driftInstrument reading outside +/-0.5% accuracyRecalibration and retest
Missing documentationTest certificates, calibration records not available at FATDelays FAT sign-off
Cosmetic damageScratched panel, damaged labelMinor—punch list item, fix before packing
Performance shortfallPump not reaching specified head at rated flowMajor—may require impeller change or redesign

FAT Certificate

The FAT certificate is a signed document confirming that the equipment has passed all tests. It typically includes:

SectionContent
Equipment tagTag number per P&ID
PO referencePurchase order number
Test dateDate(s) FAT was conducted
Tests performedList referencing FAT procedure clauses
ResultsPass/fail per test with recorded values
Punch listOutstanding items (if any) with closure deadlines
SignaturesVendor QA, buyer representative, TPI (if applicable)

The signed FAT certificate authorizes shipment. Without it, the equipment should not be released. For procurement documentation requirements and shipping documents needed after FAT completion, see the detailed guides.

Read the full guide to pipe classes and specifications

Advertisement

Leave a Comment

Have a question or feedback? Send us a message.

Your comment will be reviewed and may be published on this page.