Expediting is the systematic monitoring and follow-up of purchase orders from placement through delivery. The expediter tracks the vendor’s manufacturing progress, identifies potential delays, escalates issues, and takes corrective action to ensure materials arrive at site on time. Expediting is a core procurement function in EPC projects where late material delivery directly delays construction milestones.

A typical EPC piping project has 100-400 active purchase orders running simultaneously. Without structured expediting, delays accumulate undetected until materials fail to arrive at site.

Types of Expediting

TypeMethodFrequencyBest For
Desk expeditingPhone, email, vendor portalWeekly or bi-weeklyStandard commodity orders (pipes, fittings, flanges)
Field expeditingPhysical visit to vendor’s facilityMonthly or at key milestonesCritical and long-lead items (valves, specialty alloys)
Emergency expeditingIntensive daily follow-up, escalation to managementAs neededOrders at risk of critical delay

Expediting Milestones

Expediters track progress against predefined milestones. Each milestone has an expected date per the PO delivery schedule.

MilestoneDescriptionTypical Checkpoint
PO acknowledgmentVendor confirms acceptance of PO termsWeek 1
Raw material procurementSteel billets, plates, forgings ordered and receivedWeek 2-6
Manufacturing startProduction begins (rolling, forging, machining)Week 4-8
In-process inspectionHold/witness point per ITPDuring manufacturing
Manufacturing completeAll items produced and ready for final inspectionWeek 8-16
Final inspectionThird-party release inspection1-2 weeks after completion
Packing and markingItems packed per PO requirements, shipping marks applied1 week after release
ShipmentGoods dispatched per IncotermsPer PO schedule
Document submissionMTCs, test reports, shipping documents submittedWithin 2-4 weeks of shipment

Expediting Report

Expediters issue periodic status reports to the project team. A standard report includes:

Report FieldContent
PO numberReference number
VendorSupplier name and location
Item descriptionMaterial type and key specs
PO quantityOrdered quantity
Promised deliveryContractual delivery date
Current statusManufacturing stage, % complete
Forecast deliveryUpdated estimate based on current progress
VarianceDays ahead or behind schedule
Risk levelGreen / Amber / Red
Action requiredEscalation, alternative sourcing, acceleration

Common Causes of Vendor Delay

CauseFrequencyMitigation
Raw material shortageHighVerify vendor’s material stock before PO or during kick-off meeting
Production capacity overloadMediumCheck vendor’s order backlog during bid evaluation
Inspection failure / reworkMediumReview vendor’s quality history; specify clear ITP with hold points
Sub-supplier delayMediumRequest sub-supplier list and lead times during TBE
Documentation delaysHighSet document submission milestones with penalties in PO
Shipping / logistics issuesMediumConfirm vessel booking 4-6 weeks before shipment

Effective expediting is preventive, not reactive. The expediter identifies problems before they affect the project schedule. For the procurement documents that drive the expediting process and hydrostatic testing milestones that affect manufacturing timelines, see the detailed guides.