What Is Expediting? Order Follow-Up
Expediting is the systematic monitoring and follow-up of purchase orders from placement through delivery. The expediter tracks the vendor’s manufacturing progress, identifies potential delays, escalates issues, and takes corrective action to ensure materials arrive at site on time. Expediting is a core procurement function in EPC projects where late material delivery directly delays construction milestones.
A typical EPC piping project has 100-400 active purchase orders running simultaneously. Without structured expediting, delays accumulate undetected until materials fail to arrive at site.
Types of Expediting
| Type | Method | Frequency | Best For |
|---|---|---|---|
| Desk expediting | Phone, email, vendor portal | Weekly or bi-weekly | Standard commodity orders (pipes, fittings, flanges) |
| Field expediting | Physical visit to vendor’s facility | Monthly or at key milestones | Critical and long-lead items (valves, specialty alloys) |
| Emergency expediting | Intensive daily follow-up, escalation to management | As needed | Orders at risk of critical delay |
Expediting Milestones
Expediters track progress against predefined milestones. Each milestone has an expected date per the PO delivery schedule.
| Milestone | Description | Typical Checkpoint |
|---|---|---|
| PO acknowledgment | Vendor confirms acceptance of PO terms | Week 1 |
| Raw material procurement | Steel billets, plates, forgings ordered and received | Week 2-6 |
| Manufacturing start | Production begins (rolling, forging, machining) | Week 4-8 |
| In-process inspection | Hold/witness point per ITP | During manufacturing |
| Manufacturing complete | All items produced and ready for final inspection | Week 8-16 |
| Final inspection | Third-party release inspection | 1-2 weeks after completion |
| Packing and marking | Items packed per PO requirements, shipping marks applied | 1 week after release |
| Shipment | Goods dispatched per Incoterms | Per PO schedule |
| Document submission | MTCs, test reports, shipping documents submitted | Within 2-4 weeks of shipment |
Expediting Report
Expediters issue periodic status reports to the project team. A standard report includes:
| Report Field | Content |
|---|---|
| PO number | Reference number |
| Vendor | Supplier name and location |
| Item description | Material type and key specs |
| PO quantity | Ordered quantity |
| Promised delivery | Contractual delivery date |
| Current status | Manufacturing stage, % complete |
| Forecast delivery | Updated estimate based on current progress |
| Variance | Days ahead or behind schedule |
| Risk level | Green / Amber / Red |
| Action required | Escalation, alternative sourcing, acceleration |
Common Causes of Vendor Delay
| Cause | Frequency | Mitigation |
|---|---|---|
| Raw material shortage | High | Verify vendor’s material stock before PO or during kick-off meeting |
| Production capacity overload | Medium | Check vendor’s order backlog during bid evaluation |
| Inspection failure / rework | Medium | Review vendor’s quality history; specify clear ITP with hold points |
| Sub-supplier delay | Medium | Request sub-supplier list and lead times during TBE |
| Documentation delays | High | Set document submission milestones with penalties in PO |
| Shipping / logistics issues | Medium | Confirm vessel booking 4-6 weeks before shipment |
Effective expediting is preventive, not reactive. The expediter identifies problems before they affect the project schedule. For the procurement documents that drive the expediting process and hydrostatic testing milestones that affect manufacturing timelines, see the detailed guides.